The company signed a contract with the Egyptians Orascom company for the completion of the steel structure of the cement Bazian project, duration of the termination of the project (8) months and the total amount for the installation of the metal on the building of is (1450) tones, at a daily rate of is (6971)kilo gram has been installed at the building, as the company’s ability to connect the amount of 60 tons per day, and (4) cranes used by AMIRCO to complete the project, and the number of workers engaged in the project is (60) workers. |
||